Five projects are changing the middle of the city. One is finished. Two should land this year. Two run into 2027.

When five Detroit projects landThe Gordie Howe bridge is open. Monroe Street is due in fall 2026 and the Michigan Central hub in 2026. The life sciences building and the Detroit City FC ground run into 2027.202520262027nowGordie Howe bridgeMonroe StreetMichigan Central hubLife sciences buildingDetroit City FC ground
The Gordie Howe International Bridge across the Detroit River Open

Gordie Howe International Bridge

Delray to Windsor · 2026

A publicly owned cable-stayed crossing to Canada, the first new road bridge between Detroit and Windsor since the Ambassador opened in 1929. Canada funded construction and recovers it through tolls.

Worth noting. It missed a September 2025 target. Reporting at the turn of the year had it 98 per cent complete and projected to open as early as the first quarter of 2026.

Source: crainsdetroit.com · Photograph: WMrapids · CC0
Shopfronts along Monroe Street in Greektown Finishing

Monroe Street rebuild

Greektown · Due fall 2026 · $20 million

Greektown's main thoroughfare rebuilt as a pedestrian-first street rather than a road with sidewalks attached. Work began in March 2025.

Source: hourdetroit.com · Photograph: PDru2014 from Detroit, United States · CC BY 2.0
The restored Michigan Central Station in Corktown Under way

Michigan Central multimodal hub

Corktown · Due to finish 2026

A transport hub on the Michigan Central campus intended to bring Amtrak service back to the station. Announced by Governor Whitmer.

Source: hourdetroit.com · Photograph: PunkToad · CC BY 2.0

What the city has actually issued

The biggest new buildings the city has signed off this year, from Detroit's own permit records. Updated daily.

Largest new-construction permits issued in 2026
AddressIssued Est. cost Filed description
2850 W Grand Blvd BLD2025-01010 · 19 stories 2026-04-30 $874m Phase IIl Permit for Interior Build-Out to Code to establish 19 Story Hospital per plans. See BLD2024-00886 for Phase I & all project fees & BLD2025-00042 for Phase II. Subject to…
9040 W Jefferson Ave BLD2025-01893 · 1 stories 2026-05-12 $49.8m Construct New SFE Pump Building to Code per plans. Subject to Field Approval. Separate Trade Permits required.
18875 Ryan Rd BLD2025-00085 · 1 stories 2026-01-20 $45.7m 3700 E. Seven Mile Legal. Phase II Permit to Construct New 108,000 sq ft, 1 story High School (Pershing High), Athletic Fields, & Site Work to Code per plans. See BLD2024-01852 for…
25 Cadillac Sq BLD2025-00874 · 3 stories 2026-01-05 $42.5m Construct New 70,000 sq ft, 3-Story, 1,600 seat immersive Theater (Entertainment Venue) w/On-Site Consumption & associated Site Work to Code per plans. Subject to Field Approval…
900 Dickerson St BLD2024-02538 · 2 stories 2026-04-17 $29m Construct New 2 Story, 71,445 sq ft 2 Story Pre-K thru 8 School to Code per plans. Subject to Field Approval, Separate Trade, DPW Right-of-Way, & DWSD Permits required.
1326 Saint Antoine St BLD2025-03016 · 2 stories 2026-02-04 $27.6m Partial Permit for Core and Shell 2 Story, 89,050 sq ft Office Bldg to include MEP's to Code per plans. Separate Tenant Permit required. Subject to Field Approval. Separate Trade, DPW…

Descriptions are the applicant's own filed wording, quoted rather than summarised. A permit is a filing, not a promise: some of these will not be built. Permits updated automatically 7 hours ago

Source: data.detroitmi.gov · building permits register

Still to break ground

Breaking ground

Life sciences building

The old county jail site · Start 2026, finish 2027

Bedrock's building on the site of the abandoned Wayne County jail project, cut from five stories to two. BAMF Health takes the ground floor.

Source: crainsdetroit.com ·
Breaking ground

Detroit City FC stadium

Southwest Detroit · Takes shape 2026 · $198 million

A stadium and housing development for the supporter-owned club.

Source: crainsdetroit.com ·
A platform inside a Detroit People Mover station
The People Mover, which has circled downtown since 1987. Mx. Granger · CC0, via Wikimedia Commons

The part nobody puts on a render

Every project on this page is a building or a road. Getting between them is the older problem, and the Michigan Central hub is the only item on the list that is really about movement — it is meant to bring Amtrak back to the station.

Source: hourdetroit.com ·

Longer pieces on this

Everything we have written →

How to read this page

Everything here links to where it came from — follow any source and check it yourself. Scores, listings and permits update on their own through the day. Anything written by a person carries the date it was last checked, so you can see how fresh it is before you rely on it. If something looks wrong, it might be: tell us and we will correct it in the open.